VR Flight Simulator Installation and Commissioning: What to Expect, Step by Step

Installing a VR flight simulator takes seven steps: prepare the site, receive and inspect the delivery, assemble the machine, connect power, set up the VR hardware and content, run commissioning tests, then train your staff and complete the handover. Most problems come from skipped site checks, so get the installation requirements from your supplier before the machine ships.
Key takeaways
- Ask for an installation requirements sheet and a layout drawing before you order.
- Check the floor, ceiling height, power supply, door width and lifting access before delivery.
- Inspect crates when they arrive, photograph any damage and report it quickly.
- Have a qualified electrician do the power connection.
- Do not open to the public until commissioning tests, staff training and handover documents are complete.
The installation process at a glance
| Step | What happens | Who is usually responsible |
|---|---|---|
| 1. Site preparation | Floor, power, access and layout are checked and prepared | Buyer, using the supplier’s requirements sheet |
| 2. Delivery and inspection | Crates arrive; contents and condition are checked | Buyer and delivery team |
| 3. Unpacking and assembly | Machine is assembled in its final position | Buyer’s team with supplier guidance, or supplier’s engineer |
| 4. Electrical connection | Machine is connected to the power supply and earthing | Qualified electrician |
| 5. VR hardware and content | Headsets, controls and software are set up and updated | Supplier guidance with buyer’s operator |
| 6. Commissioning and testing | Safety and function tests are run and recorded | Buyer and supplier together |
| 7. Training and handover | Staff are trained; documents are handed over | Supplier and buyer |
Step 1: Prepare the site
Good preparation saves the most time and money. Ask your supplier for an installation requirements sheet and a layout drawing for your model, then check each item below against it.
| Check | What to confirm |
|---|---|
| Floor area | Enough space for the machine, safe clearance around it, the queue area and a staff station |
| Floor condition | Level, strong and suitable for the machine’s weight and any fixing method the manual requires |
| Ceiling height | Enough clearance for the machine’s full range of motion and for installation |
| Power supply | Correct voltage, phase, capacity, outlet or breaker, and proper earthing for your region |
| Access route | Entrances, corridors, lifts and doors wide and tall enough for the crates |
| Lifting and moving | Forklift, pallet jack or lifting equipment and trained people available on the day |
| Environment | Temperature, ventilation, lighting and a reasonably dust-free area |
| Network | If your content or management system needs internet, check the connection |
| Signage and queue | Space for rider limit signs, a briefing point and a waiting area |
| Approvals | Any local permit, inspection or landlord approval you need before installing |
If you have not finalized a model yet, our guides on 2-seat vs 3-seat VR flight simulators and VR sky glider vs VR parachute simulator will help you match space and audience.

Step 2: Receive and inspect the delivery
- Check the shipment before signing. Compare the number and condition of crates with the packing list.
- Look for damage. Check for crushed corners, water marks and tilted or opened crates.
- Take photos and video. Record the crates before and after opening, in case you need to claim.
- Report problems promptly. Note any damage on the delivery paperwork and tell your supplier and carrier right away.
- Store parts safely. Keep small parts, headsets and electronics in a dry, secure place until assembly.
Step 3: Unpack and assemble
Follow the assembly instructions for your model. In general:
- Unpack in or near the final position to avoid moving heavy parts twice.
- Lay parts out and match them against the parts list before you begin.
- Use the tools and the number of people the manual recommends, and wear suitable protective equipment.
- Tighten fasteners to the specified torque, and mark them if the manual advises.
- Route cables carefully so they are protected and cannot be pinched by moving parts.
- Photograph each stage in case you need remote support later.
Many buyers use remote video guidance from the supplier, an assembly manual and video, or an engineer on site. Ask which of these options apply to your order before you buy.
Step 4: Connect power safely
Electrical work should be done by a qualified electrician who follows the wiring diagram and your local rules. Make sure of the following:
- The supply matches the machine’s required voltage and capacity.
- Earthing and protective devices are installed correctly.
- The emergency stop is wired and tested before any motion test.
- Cables, plugs and connectors are in good condition and protected from damage.
Step 5: Set up the VR hardware and content
- Install and check the headsets, fit adjustments and cleaning surfaces.
- Install the content and check that each title plays correctly and in the right language.
- Check the control system, the operator interface and any payment or ticket integration you plan to use.
- Confirm how updates are delivered, and how often.
- Record login details and licenses in a safe place that your venue manager can access.
Step 6: Commissioning and testing
Commissioning is where you prove that the machine is safe and ready. Follow the procedure in the manual and record each result. Typical tests include:
| Test | What to confirm |
|---|---|
| Visual and mechanical inspection | All parts are fitted, fasteners are tight, nothing rubs or catches |
| Emergency stop | Stops the machine promptly from every operator position |
| Empty cycle | Motion is smooth, within limits, and the machine returns to its safe position |
| Restraint checks | Belts, bars and locks work and can be released safely |
| Loaded run | Machine runs correctly with the loads the manual specifies, then with trained staff riding |
| Headset and content | Image is sharp, motion matches the picture, sound is clear |
| Sensors and limits | Safety limits and interlocks respond as expected |
| Documentation | Test results are written, dated and signed |
If any test fails, stop and fix it before you continue. Do not run the ride for the public until every item has passed. See our guide to VR flight simulator safety, CE and insurance for the documents, daily checks and operator training that go with commissioning.
Step 7: Train staff and hand over
Staff training
- Daily start-up and shut-down routine
- Rider limits and the safety briefing
- Seating, headset fitting and restraint checks
- Emergency stop and evacuation routine
- Cleaning, basic troubleshooting and when to call support
Documents to receive at handover
- User manual and maintenance schedule
- Wiring diagram and electrical specification
- Certificates and test reports that apply to your market
- Rider limits sheet
- Spare parts list and warranty terms
- Support contact details and response expectations
- A copy of the commissioning test record
Common installation problems and how to avoid them
| Problem | How to avoid it |
|---|---|
| Crates do not fit through the door or lift | Measure the access route and compare with the crate sizes before shipping |
| Ceiling or clearance too low | Check the full range of motion, not only the machine’s resting height |
| Wrong plug, voltage or capacity | Confirm the electrical specification for your country before production |
| Damaged goods on arrival | Inspect, photograph and report immediately |
| Missing or unclear instructions | Request the manual and installation video before delivery |
| Opening before testing is complete | Set a rule: no public rides until all commissioning tests are signed off |
| Staff not trained | Schedule training before the opening date, and keep records |
Before you order: questions to ask the supplier
- Can I see the installation requirements sheet and layout drawing for my model?
- How are crates packed, and what are their sizes and weights?
- What installation support is available: manual, video, remote guidance or an engineer on site? What does each cost?
- What tools, lifting equipment and number of people are needed?
- What is the electrical specification for my country?
- What commissioning tests do you recommend, and can you provide a test form?
- What training is included for my staff?
- How fast can you respond to installation questions in my time zone?
For purchase information and quotations, see our VR parachute simulator for sale page, or the product pages for the 3 Seats VR Parachute Simulator and the 2 Seats VR Sky Glider Simulator. To see how a supplier builds and tests machines before you order, read our checklist on how to visit a VR simulator factory in China.

See the machines and the build process in person
Our factory is in Panyu District, Guangzhou, about 30 minutes by car from the Canton Fair venue, depending on traffic. You can ride the machines, see how they are assembled and tested, and talk to our team about installation for your venue.
Book a visit or ask about installation
- Phone / WhatsApp: +86 18122722483
- Email: [email protected]
- Address: 202, Floor 2-3, No 5th Shixin Rd, Xinshuikeng Village, Dalong Street, Panyu District, Guangzhou, China
Please send your name, country, venue size, preferred date and the models you are considering. We recommend contacting us at least one day ahead for a visit.
Frequently asked questions
How is a VR flight simulator installed?
Installation usually follows these steps: prepare the site, receive and inspect the delivery, unpack and assemble the machine, connect power by a qualified electrician, set up the VR hardware and content, run commissioning tests, train staff and complete a handover. Always follow the manufacturer’s manual for your model.
What should I prepare before the machine arrives?
Prepare a level floor of the right size, check ceiling height, confirm the power supply and earthing, make sure doors and corridors are wide enough for the crates, arrange lifting equipment, and plan the queue area and signage. Ask your supplier for a layout drawing and an installation requirements sheet.
Do I need an engineer on site for installation?
It depends on the model, your team’s experience and the supplier’s service. Some buyers install with remote video guidance, others prefer an engineer on site. Ask your supplier which options are available for your order and what they cost.
What tests should be done before opening to the public?
Typical tests include empty-cycle runs, emergency stop, restraint and lock checks, motion limits, headset and content checks, and a full run-through with trained staff. Follow the commissioning procedure in the manual and record the results.
What documents should I receive at handover?
Ask for the user manual, maintenance schedule, wiring diagram, certificates for your market, spare parts list, warranty terms and contact details for support. Keep a copy of the commissioning test record.
Can I see how a VART machine is assembled before I order?
Yes. Visit the VART factory in Panyu District, Guangzhou, to see the machines and the assembly and testing process. Message us on WhatsApp at +86 18122722483 or email [email protected] to book a visit.
Final thoughts
A smooth installation is mostly decided before the machine ships: confirm the site requirements, agree what support the supplier provides, and plan your testing and training. Take your time with commissioning, keep records, and open only when everything has passed. If you share your venue details with us, we can help you prepare the site and plan the installation.